MOPA INTERNATIONAL AIRPORT HIGHLIGHTS

Development in four phases.Phase-wise design capacityPhase One: 4.4 mppa
Phase Two: 5.8 mppa
Phase Three: 9.4 mppa
Phase Four: 13.1 mppa
Ultimate potential: 28 mppa
mppa: million passenger per annum.
Traffic trigger for phase-wise developmentUpon achieving 80% design capacity of previous phase.
HangarsOne
TerminalOne
Aprons/RampsAprons are planned to park 18 Code C aircrafts in Phase1 development.
TaxiwaysTaxiways are planned as per details below in phase 1 development.
1 TWY North Full length parallel taxiway
2 TWY A1-A8 All 8 taxiways (6 cross taxiways and 2 rapid exit taxiways). A1 and A8 are for Code F aircraft.
3 Taxi lanes Taxi lanes for 18 aircraft stands
RunwayRunway (09 – 27) will be constructed for Code E in the initial phase which will be augmented for code F in phase 3, which will enable operation of Airbus A380.
Authority HangarAdequate space for parking of 2 ( two ) code C aircraft’s ( Aeroplane & Helicopter )

Accessibility| SiteMap| Privacy Policy| Terms| Disclaimer| Copyright
© 2024: Department of Civil Aviation..GoG | Last Updated on: 04/07/2023 | Designed and Maintained by: Info Tech Corporation of Goa Limited.
Page Reader Press Enter to Read Page Content Out Loud Press Enter to Pause or Restart Reading Page Content Out Loud Press Enter to Stop Reading Page Content Out Loud Screen Reader Support